DI Migration Process Overview
Overview
Provides an overview of the DI Migration process.
The migration process consists of the steps indicated in the guidepost. Each step consists of one or more tasks.
- Prepare Migration Plan: Prepare your migration strategy.
- Prepare Environment: Install the 5.x.x version of the server, download and unpack the Migration Tool.
- Export Data From 4.4.x Server: Use the Migration Tool to export data from the 4.4.x server to migration bundle file.
- Import Data To 5.x.x Server: Use the Migration Tool to import migration bundle file to the 5.x.x server. Manually migrate additional data, as needed.
- Verify migration: Use checklists to test that migration was completed properly.
- Next Steps: Indicates what to do after the migration process is complete.